Kauri Flats

School Build

See the progress being made on site.

Due to politics of many and very poor geo tech of the land the school programme was delayed by 6 months. Fortunately, we know the school will not sink now and will not be rushed to be built, so we get an outstanding building.

We are on track for full opening by September 2017 and two thirds of the school open late July 2017.

Work Begins...!

Thumbnail: Work Begins...!
3 Images

Test Piling is now complete with the school being built off site to be transported to Walters Road stage by stage!

Progress update w/b 15/08

Thumbnail: Progress update w/b 15/08
12 Images

Civil works on site...

The site

Thumbnail: The site
45 Images

The site of Kauri Flats School...

Blessing of the Soil

Thumbnail: Blessing of the Soil
1 Images

Tuesday 23 February: At 6am the first sod of soil was turned and the development of Kauri Flats School began. Led by Kaumatua Bob Clark from Te Akitai Waiohua the first soil was turned by Hon.Judith Collins. Thank you to all of the 30+ guests for your attendance that morning and continued support.

Geotech for Piling

Thumbnail: Geotech for Piling
4 Images

Monday 9 May: Work has started on site!!! Preparation for piling and earthworks are now being undertaken by Decmil, the school's construction company.